TNEB Limited||TANGEDCO||CE-MTPS-I - TANGEDCO||SE-Mechanical Maintenance I-MTPS-I - TANGEDCO |
| Tender Reference Number |
CE / MTPS-I / SE / M-I / MP /OT.324 /2024-25 |
| Tender ID |
2025_EB_536455_1 |
Withdrawal Allowed |
No |
| Tender Type |
Open Tender |
Form Of Contract |
Works |
| Tender Category |
Works |
No. of Covers |
1 |
| General Technical Evaluation Allowed |
No |
ItemWise Technical Evaluation Allowed |
No |
| Payment Mode |
Online |
Is Multi Currency Allowed For BOQ |
No |
| Is Multi Currency Allowed For Fee |
No |
Allow Two Stage Bidding |
No |
|
|
|
|
|
| 1 |
Fee/PreQual/Technical/Finance |
EMD Details |
.pdf |
|
|
BQR Evidences |
.pdf |
|
|
Other Technical Documents |
.pdf |
|
|
Price Bid |
.xls |
|
|
|
|
|
| |
|
|
| |
| Tender Fee in ₹
|
0.00 |
| Fee Payable To |
Nil |
Fee Payable At |
Nil |
| Tender Fee Exemption Allowed |
No |
|
|
| EMD Amount in ₹
|
6,200 |
EMD Exemption Allowed |
Yes |
| EMD Fee Type |
fixed |
EMD Percentage |
NA |
| EMD Payable To |
Nil |
EMD Payable At |
Nil |
| BG Required |
Yes |
eBG Required |
Yes |
| Minimum Direct EMD Payment in ₹ |
0.00 |
|
|
|
| |
|
|
| |
| Title |
MTPS I Mill Plant Unit III Complete dismantling and reassembling of bowl assembly worm gear housing, worm wheel mill bottom insulation cover plates broken main vertical shaft renewal of vertical shaft and its bearings etc in Coal Mill 3F Tilting |
| Work Description |
MTPS I Mill Plant Unit III Complete dismantling and reassembling of bowl assembly worm gear housing, worm wheel mill bottom insulation cover plates broken main vertical shaft renewal of vertical shaft and its bearings etc in Coal Mill 3F Tilting |
| NDA/Pre Qualification |
As per the Tender Specifications |
| Independent External Monitor/Remarks |
NA |
| Tender Value in ₹ |
NA |
Product Category |
Power/Energy Projects/Products |
Sub category |
NA |
| Contract Type |
Tender |
Bid Validity(Days) |
180 |
Period Of Work(Days) |
30 |
| Location |
Mettur Thermal Power Station-I / Mettur Dam |
Pincode |
636406 |
Pre Bid Meeting Place |
NA |
| Pre Bid Meeting Address |
NA |
Pre Bid Meeting Date |
NA |
Bid Opening Place |
Office of the Superintending Engineer /M-I/MTPS-I |
| Should Allow NDA Tender |
No |
Allow Preferential Bidder |
No |
| Enable Media Publish Date |
No |
Enable Tender Bulletin Date |
No |
|
| |
| Published Date |
28-Mar-2025 06:00 PM |
Bid Opening Date |
01-Apr-2025 02:30 PM |
| Document Download / Sale Start Date |
28-Mar-2025 06:00 PM |
Document Download / Sale End Date |
31-Mar-2025 02:00 PM |
| Clarification Start Date |
NA |
Clarification End Date |
NA |
| Bid Submission Start Date |
28-Mar-2025 06:00 PM |
Bid Submission End Date |
31-Mar-2025 02:00 PM |
|
|
|
| NIT Document |
| 1 |
Tendernotice_1.pdf
|
MTPS I Mill Plant Unit III Complete dismantling and reassembling of bowl assembly worm gear housing, worm wheel mill bottom insulation cover plates broken main vertical shaft renewal of vertical shaft and its bearings etc in Coal Mill 3F Tilting work
|
951.70
|
|
|
Download as zip file
|
| Work Item Documents |
| 1 |
BOQ |
BOQ_638419.xls
|
MTPS I Mill Plant Unit III Complete dismantling and reassembling of bowl assembly worm gear housing, worm wheel mill bottom insulation cover plates broken main vertical shaft renewal of vertical shaft and its bearings etc in Coal Mill 3F Tilting work |
358.50 |
|
|
|
| |
| Name |
Superintending Engineer /Mechanical-I/MTPS-I |
| Address |
Office of the Superintending Engineer /
Mechanical -I
Mettur Thermal Power Station- I
Mettur Dam-636406
|
|
| |
|
|
| |