Organisation Chain Kerala State Electricity Board||Chief Engineer - Transmission South||Dpty Chief Engg Trans Circle Trivandrum||EE Trans Div Trivandrum
Tender Reference Number 01/AEE/TSD-PH/BLPM/2025-26
Tender ID 2025_KSEB_820888_1 Withdrawal Allowed Yes
Tender Type Open Tender Form Of Contract Percentage
Tender Category Works No. of Covers 3
General Technical Evaluation Allowed No ItemWise Technical Evaluation Allowed No
Payment Mode Online Is Multi Currency Allowed For BOQ No
Is Multi Currency Allowed For Fee No Allow Two Stage Bidding No
 
Online Bankers
S.No Bank Name
1 SBI MOPS
Cover No Cover Type Description Document Type
1 Fee Duly signed Bounden Agreement, Bid Form Agreement, NIT, and EMD and Bid document fee details .pdf
2 PreQual/Technical Scanned copy of digitally signed Tender documents, Experience, Annexures-1 to 3 and 6 to 14 .pdf
3 Finance BOQ .xls
 
Document download date is not begun yet. You can not download the documents
 
 
Tender Fee in ₹ 1,534
Fee Payable To Nil Fee Payable At Nil
Tender Fee Exemption Allowed No
EMD Amount in ₹ 15,400 EMD Exemption Allowed No
EMD Fee Type fixed EMD Percentage NA
EMD Payable To Nil EMD Payable At Nil
 
 
Title Providing additional 11kV feeder outlet
Work Description Capital work of 110kV Substation, Balaramapuram- Providing additional 11kV feeder outlet for distribution wing at 110kV Substation, Balaramapuram
NDA/Pre Qualification Please refer Tender documents.
Independent External Monitor/Remarks NA
Tender Value in ₹ 6,13,649 Product Category Electrical Works Sub category NA 
Contract Type Tender Bid Validity(Days) 180 Period Of Work(Days) 30 
Location 110kV Substation, Balaramapuram Pincode 695501 Pre Bid Meeting Place NA 
Pre Bid Meeting Address NA  Pre Bid Meeting Date NA  Bid Opening Place Transmission Sub Division, Power House, Trivandrum
Should Allow NDA Tender No  Allow Preferential Bidder No
 
Published Date 21-Nov-2025 10:00 AM Bid Opening Date 31-Dec-2025 11:00 AM
Document Download / Sale Start Date 24-Nov-2025 11:00 AM Document Download / Sale End Date 20-Dec-2025 05:00 PM
Clarification Start Date NA Clarification End Date NA
Bid Submission Start Date 01-Dec-2025 11:00 AM Bid Submission End Date 20-Dec-2025 05:00 PM
 
NIT Document
S.No Document Name Description Document Size (in KB)
1 Tendernotice_1.pdf Tender documents 559.10
2 Tendernotice_2.pdf Notice Inviting Tender 126.88
Work Item Documents
S.No Document Type Document Name Description Document Size (in KB)
1 BOQ BOQ_1376366.xls Digital Signature BOQ 404.00
 
Name Assistant Executive Engineer
Address Transmission Sub Division, Power House, Power House Building, Thiruvananthapurm-695036.
 
 
Click Here For Main Source